Registration and first inspection of new Boilers and renewal of certificate (385).

Registration and first inspection of new Economiser and renewal of certificate (533).

For scrutiny of manufacturing drawings(393 d & 393-A)

Inspection of pipes, valves and flanges(395-B,C)

Inspection of Feed water heaters and other fittings(395-D,E)

 

 

Registration and first inspection of new Boilers and renewal of certificate.

* Registration and first inspection of new Boilers (385). 


 SR. NO.

                                                                                             FOR BOILER RATING


 
RS.

 1.

Not exceeding 10 square meter

 600/=

 2.

Exceeding 10 square meter, but not exceeding 30 square meter

            800/=

 3.

Exceeding 30 square meter, but not
exceeding 50 square meter

900/=

 4.

Exceeding 50 square meter, but not
exceeding 70 square meter

1100/=

 5.

Exceeding 70 square meter, but not
exceeding 90 square meter

1300/=

 6.

Exceeding 90 square meter, but not exceeding 110 square meter

1500/=

 7.

Exceeding 110 square meter, but not exceeding 200 square meter

1700/=

 8.

Exceeding 200 square meter, but not exceeding 400 square meter

1900/=

 9.

Exceeding 400 square meter, but not exceeding 600 square meter

2200/=

10.

Exceeding 600 square meter, but not exceeding 800 square meter

2400/=

11.

Exceeding 800 square meter, but not exceeding 1000 square meter

2700/=

12.

Exceeding 1000 square meter, but not exceeding 1200 square meter

3200/=

13.

Exceeding 1200 square meter, but not exceeding 1400 square meter

3600/=

14.

Exceeding 1400 square meter, but not exceeding 1600 square meter

4200/=

15.

Exceeding 1600 square meter, but not exceeding 1800 square meter

4500/-

16.

Exceeding 1800 square meter, but not exceeding 2000 square meter

5000/=

17.

Exceeding 2000 square meter, but not exceeding 2200 square meter

5400/=

18.

Exceeding 2200 square meter, but not exceeding 2400 square meter

6000/=

19.

Exceeding 2400 square meter, but not exceeding 2600 square meter

6300/=

20.

     Exceeding 2600 square meter, but not 
           exceeding 2800 square meter

6800/=

21.

Exceeding 2800 square meter, but not exceeding 3000 square meter

7200/=

 

Above 3000 for every 200 or part thereof an additional fee of Rs. 200 shall be charged.  


[
* According to the India Boiler (Third Amendment) Regulation, 1999.] TOP


*
Inspection Fees for renewal of certificate of Boilers shall be calculated on the basis of ratio and shall be levied in accordance to the following scale:

SR. NO.

  FOR BOILER RATING

  RS.

1.

Not exceeding 10 square meter

560/=

2.

Exceeding 10 square meter, but not exceeding 25 square meter

680/=

3.

Exceeding 25 square meter, but not
exceeding 50 square meter

800/=

4.

Exceeding 50 square meter, but not
exceeding 75 square meter

920/=

5.

Exceeding 75 square meter, but not
exceeding 100 square meter

1040/=

6.

Exceeding 100 square meter, but not exceeding 150 square meter

1280/=

7.

Exceeding 150 square meter, but not exceeding 200 square meter

1900/=

8.

Exceeding 400 square meter, but not exceeding 400 square meter

2200/=

9.

Exceeding 400 square meter, but not exceeding 600 square meter

2500/=

10.

Exceeding 600 square meter, but not exceeding 800 square meter

2800/=

11.

Exceeding 800 square meter, but not exceeding 1000 square meter

3200/=

12.

Exceeding 1000 square meter, but not exceeding 1200 square meter

3600/=

13.

Exceeding 1200 square meter, but not exceeding 1400 square meter

4000/=

14.

Exceeding 1400 square meter, but not exceeding 1600 square meter

4500/=

15.

Exceeding 1600 square meter, but not exceeding 1800 square meter

6000/=

16.

Exceeding 1800 square meter, but not exceeding 2000 square meter

6600/=

17.

Exceeding 2000 square meter, but not exceeding 2200 square meter

7200/=

18.

Exceeding 2200 square meter, but not exceeding 2400 square meter

7800/=

19.

Exceeding 2400 square meter, but not exceeding 2600 square meter

8400/=

20.

Exceeding 2600 square meter, but not exceeding 2800 square meter

9000/=

21.

Exceeding 2800 square meter, but not exceeding 3000 square meter

9600/=

 Above 3000 square meter for every 200 square meter or part thereof an additional fee of Rs. 240/= shall be charged. Fee for ordinary inspection of miniature boiler shall be Rs.120/=.  

[ * These rules may be called the Gujarat Boiler (Amendment) Rules, 2000.]  

TOP

Registration and first inspection of new Economiser and renewal of certificate

* Registration fees for new Economiser(533).

Sr. no.

  ECONOMISER RATING

Rs.

1.

Not exceeding 50 square meter
 

500/= 

2.

Exceeding 50 square meter 
But not exceeding 100 square meter

600/=

3.

Exceeding 100 square meter
But not exceeding 150 square meter

700/=

4.

Exceeding 150 square meter
But not exceeding 200 square meter

800/=

5.

Exceeding 200 square meter
But not exceeding 250 square meter

900/=

6.

Exceeding 250 square meter
But not exceeding 300 square meter

950/=

7.

Exceeding 300 square meter
But not exceeding 350 square meter

1000/=

8.

Exceeding 350 square meter
But not exceeding 400 square meter

1100/=

9.

Exceeding 400 square meter
But not exceeding 450 square meter

1200/=

10.

Exceeding 450 square meter
But not exceeding 500 square meter

1300/=

11.

Exceeding 500 square meter
But not exceeding 600 square meter

1400/=

12.

Exceeding 600 square meter
But not exceeding 700 square meter

1500/=

13.

Exceeding 700 square meter
But not exceeding 800 square meter

1600/=

14.

Exceeding 800 square meter
But not exceeding 900 square meter

1700/=

15.

Exceeding 900 square meter
But not exceeding 1000 square meter

1800/=

Above 1000 rating for every 200 or part thereof, an additional fees of Rs. 100/- shall be charged.  

[
* According to the Indian Boiler (Third Amendment) Regulation, 1999.] 

TOP

* The fees for the issue of renewal certificate of Economiser.

Sr. no.  

  ECONOMISER RATING

RS.  

1.

Not exceeding 50 square meter  

400/=
 

2.

Exceeding 50 square meter 
But not exceeding 100 square meter

500/=  

3.

Exceeding 100 square meter
But not exceeding 150 square meter

600/=

4.

Exceeding 150 square meter
But not exceeding 200 square meter

700/=

5.

Exceeding 200 square meter
But not exceeding 250 square meter

800/=

6.

Exceeding 250 square meter
But not exceeding 300 square meter

1080/=

7.

Exceeding 300 square meter
But not exceeding 350 square meter

1200/=

8.

Exceeding 350 square meter
But not exceeding 400 square meter

1320/=

9.

Exceeding 400 square meter
But not exceeding 450 square meter

1440/=

10.

Exceeding 450 square meter
But not exceeding 500 square meter

1560/=

11.

Exceeding 500 square meter
But not exceeding 600 square meter

1680/=

12.

Exceeding 600 square meter
But not exceeding 700 square meter

1800/=

13.

Exceeding 700 square meter
But not exceeding 800 square meter

1920/=

14.

Exceeding 800 square meter
But not exceeding 900 square meter

2040/=

15.

Exceeding 900 square meter
But not exceeding 1000 square meter

2160/=

 Above 1000 square meter for every 20 square meter or part thereof an additional fee of Rs. 200/= shall be charged. 
 

[
* These rules may be called the Gujarat Economiser (Amendment) Rules, 2000.]

TOP

 

For scrutiny of manufacturing drawings(393 d & 393-A)

393 d :The fees for the scrutiny of the manufacturing drawings and the particulars of the materials, design and construction of boilers under sub-regulations ( a ) or ( b ) shall be on the scale prescribed in Regulation 385. When the manufacturing drawing have been scrutinized and in respect of them alterations have been suggested and the same are resubmitted for scrutiny, separate fee at the rate of 10 per cent, of the fee for the first scrutiny of the  drawings shall be payable if the manufacturing drawings contains alterations other than those previously suggested.

 393-A : Fee for Scrutiny of Manufacturing Drawings etc.:

 ( a ) The fee for scrutiny of the manufacturing drawings and the particulars of materials, design and construction of boiler under sub-regulation (a) or (b) of Regulation 393 shall be on the scale prescribed in Regulation 385. When the manufacturing drawings have been scrutinized and in respect of them alteration have been suggested is submitted for scrutiny, separate fee on the same scale shall be payable if the manufacturing drawings contain alterations other than those previously suggested.

( b ) The procedure laid down in CL. (a) above shall be followed in the case of structural alterations, addition or renewal of any part of a boiler.                  

TOP

 

Inspection of pipes, valves and flanges(395-B,C)  

* 395-B. Fees for inspection of pipes:

( a ) For the pipes of nominal bore not exceeding 100 mm inclusive of all fittings, excepting fitting like de-super heaters, steam receivers, feed heaters and separately fired super heaters—Rs. 200 for 30 meters of pipe or part thereof.

( b ) For pipes of nominal bore exceeding 100 mm inclusive of all fittings excepting fittings like de-super heaters, steam receivers, feed heaters and separately fired super heaters Rs. 500/- for 30 meters of pipe or part thereof.

( c ) Fees for inspection of fittings like de-super heaters, steam receivers, feed heaters and separately fired super heaters Rs. 500/- for each such fittings.  

[ * According to the Indian Boiler (Third Amendment) Regulations, 1999.]

* 395-C. Fee for inspection of valves:

Fees for inspection of Valves shall be charged as under:-

(1) Subject to minimum inspection fee of Rs. 500/- per inspection for the valves ,the inspection fee for valves shall be charged as under:-

      (a)   upto 25 mm                                                      Rs. 5/- per piece.

(b)    above  25 mm and upto 100 mm                     Rs. 20/- per piece.

(c)  above 100 mm and upto 250 mm                     Rs 150/- per piece..

(d)  above 250 mm                                                  Rs. 400/- per piece

 (2) Fee for inspection of flanges shall be charged as under:-

      (i)                  For forged and cast flanges, the fees shall be charged as under::

                  (a)   Upto and including  25 mm for a batch  of 50 or part thereof 
                               Rs. 120/-

(b)   Upto and including  25 mm for a batch  of 100 or part thereof Rs. 220/-

(c)   Over  25 mm upto and including 50 mm for a batch of 50 or part thereof 
Rs. 240/-

(d)   Over 50 mm upto and including 100 mm for a batch of 25 or part  thereof Rs.240/-

(e)   Over 100 mm upto and including 250 mm for a batch of 10 or part thereof Rs.260/-

(f)     Over 250 mm for a batch of 5 or part thereof  
Rs. 300/-  

       (ii)       For plate flanges: The fees shall be charged at half the rate as charged
                   for forged and cast  flanges.  
        
                   The fees shall be charged at half the rate as charged for forged and cast 
                  
flanges.  

               [ * According to the Indian Boiler (Third Amendment) Regulations, 1999.]

TOP

 

Inspection of Feed water heaters and other fittings(395-D,E)  

395-D. Fees for inspection of components of valves:-

 The fees for inspection of components of valves shall be charged as under: :-           

(i)               50% of the inspection fees of the valves shall be charged by the Chief Inspector of the State, where the components of the valves, are manufactured, for inspection of the components manufactured in a State other than the State where the valves are assembled and remaining 50% of the inspection fees shall be charged by the Chief Inspector of the State, where the valves are assemble, for inspection of assembly and final inspection of the valves.

(ii)              Where the inspection, so far as the material testing is concerned, has been carried out by a “Well-known Foundry” or “Well-known Forge” full inspection fees shall be charged by the Chief Inspector of the State were the valves have been assembled and finally tested.

(iii)            Where the components of the valves are inspected and tested in the same manufacturing work where the valves are assembled and finally tested, full inspectio